10" Subsea Hot Tapping and Line Stopping, Gulf of Mexico

Tool - SureTap Hot Tap Machine, Subsea BISEP Line Stopping Tool
Location - USA
USA location on a map
Operating Environment - Offshore Subsea
Pipeline Medium - Oil
Activity - Abandonment, Decommissioning
SubseaHotTapping&PluggingGoM

Abandoning a live subsea pipeline means cutting into a system that is still under pressure, still carrying oil, and sitting on the seabed. Get any part of that sequence wrong and the result is an uncontrolled release into the water.

Abandoning a Live Subsea Pipeline Without Releasing Oil to the Environment

In the Gulf of Mexico, at a water depth of around 25 metres, STATS was contracted to isolate and abandon a 10 inch oil pipeline as part of a decommissioning project.

The project required subsea hot tapping and line stopping at two locations to allow removal of a short section of pipework. Once isolated, purged and cut, one end of the remaining pipeline was terminated with a mechanical connector and blind flange; the other was fitted with a full bore valve and blind flange.

Highlights

  • Patented BISEP technology delivered leak-tight, dual-barrier isolation of a live, pressurised subsea pipeline at 25 metres water depth.
  • Project delivered without incident, aside from weather delays.
  • Flushing through the BISEP launcher's integrated 2 inch port avoided any release of oil to the environment before containment was broken.
  • Fewer fittings and hot taps required than traditional line stop technology, saving the client time and money.
  • Three-day de-oiling confirmed by a dewatering pig received at the barred flange before final abandonment.
123_1

BISEP Deployed Through a Single Hot Tap Fitting

STATS BISEP was deployed through a mechanical hot tap clamp and slab valve, to provide leak-tight isolation of the pressurised pipeline through a single fitting. Hydraulically activated dual seals gave fully proven, monitored isolation of the pipeline's contents throughout the project - an advantage over traditional line stop technology.

Two BISEPs, a Verified Zero-Energy Zone, and a Flush Without Breaking Containment

Once equipment and personnel were mobilised to the vessel, the slab valve and hot tap machine were attached to the mechanical hot tap clamp and lowered into position. The clamp was bolted to the pipeline and leak-tested to confirm the fitting's integrity before cutting into the live line.

With both hot taps complete, the first BISEP was lowered into position, pressure-tested against the closed slab valve, then deployed into the pipeline toward the pressure threat and hydraulically activated to create the first isolation barrier. A second BISEP was installed and deployed to create a midline isolation of the pressurised pipeline. Each BISEP was independently tested on its primary and secondary seals to verify a zero-energy zone in the seal annulus, and an Isolation Certificate was issued once testing was complete.

STATS then used the BISEP launcher's integrated 2 inch port to attach a downline from the vessel to each launcher, upstream and downstream, flushing the isolated pipe section with seawater before it was cut. This is a feature exclusive to the BISEP design: it avoided additional hot tapping and reduced the number of fittings installed on the pipeline, saving the client time and money and reducing risk to the project.

Once the section was clean, it was cut behind each BISEP and recovered to the vessel. New pipe sections, including flushing ports, a barred flange and a 10 inch ball valve, were installed at both ends. With the BISEPs still isolating the pipeline, a leak test confirmed the new pipework before both BISEPs were unset, retracted and recovered to the surface. Completion plugs were installed in the hot tap clamps and the slab valves were removed.

Aside from weather delays the project was delivered according to plan and without incident. Major benefits achieved by the client from using the BISEP over traditional line-stop technology included requiring less fittings and hot tapping on the pipeline and the ability to flush between both isolation barriers prior to breaking containment, thus avoiding any release of oil to the environment. Additionally, the design of the BISEP provides the ability to pressure test the newly installed pipework prior to introducing inventory back into the pipeline.

STATS Group logo
Spokesperson
STATS Group

A Three-Day De-Oil and a Pipeline Safely Abandoned

The client then launched a single dewatering pig from the onshore processing facility to the newly installed 10 inch ball valve; de-oiling the pipeline took three days, confirmed complete when the pig was received at the barred flange. The valve was closed, flushing hoses installed, and the pipe flushed through the new 2 inch ports to verify every trace of oil had been removed before the flushing equipment was recovered. A blind flange was installed on one end of the connector, abandoning the section of pipeline running to the onshore facility, and another was fitted to the 10 inch ball valve, securing that section and leaving it ready for future tie-ins.

This project marks a significant milestone as it is the first subsea deployment of the BISEP in the Gulf of Mexico and follows on from a previous successful subsea deployment of an Inline Weld Test Tool during 2016 for testing a critical weld in its 'live' position. We hope this will be the catalyst to drive further hot tapping and isolation work in the Gulf of Mexico where we can offer a high integrity double block and bleed isolation alternative over traditional line-stop technology.

STATS Group logo
Spokesperson
STATS Group

 

Contact Us

Tell us about your requirements