30" Dual BISEPS, Cortez Pipeline, New Mexico, USA

Tool - BISEP Line Stopping Tool, SureTap Hot Tap Machine
Location - USA
USA location on a map
Operating Environment - Onshore, Pipeline Transmission
Pipeline Medium - CO2
Activity - Maintenance, Valve Repair / Replacement
30in BISEP cw bypass with pipelines coming out of the ground

STATS Group were contracted by Kinder Morgan to provide hot tapping and line-stopping services on the 30-inch system. The successful completion of that work established a world first: the first leak-tight double block and bleed isolation of a high-pressure CO2 pipeline.

World's First Double Block and Bleed Isolation of a High-Pressure CO2 Pipeline

When a 500-mile CO2 pipeline in New Mexico needed upgrading, the operator faced a challenge that had never been attempted before.

At 148 bar (2,140 psi) and ambient temperature, the carbon dioxide flowing through the Cortez Pipeline exists in a supercritical fluid state. Isolating it safely - without halting delivery to downstream customers - required engineering that simply had no precedent.

Highlights

  • World first - the first successful leak-tight double block and bleed isolation of a high-pressure CO2 pipeline.
  • Four isolation sites completed on the 500-mile Cortez CO2 pipeline for Kinder Morgan.
  • 160-plus days of cumulative BISEP isolation time, with zero seal degradation.
  • No leaks past the primary barrier across all interventions.
  • CO2 venting methodology developed by STATS - controlled blowdown and nitrogen annulus purge to prevent solid CO2 formation and protect seal integrity.
  • Production maintained throughout using a 24-inch bypass line.
People working on a 24” bypass line installation

Converting a Live CO2 Pipeline With No Room for Error

The Cortez Pipeline runs 500 miles from source fields in southwestern Colorado to Denver City, delivering CO2 used primarily for enhanced oil recovery. As part of a larger programme to convert the system from a non-piggable to a piggable pipeline, Kinder Morgan needed to install full-bore inline valves and retrofit pigging launchers and receivers - all without interrupting pipeline operation.

The operating conditions made this unlike any previous line-stop project. CO2 at pipeline pressure and ambient temperature behaves as a supercritical fluid: when vented to atmospheric pressure it flashes to vapour, with a sharp temperature drop that can produce solid CO2 (dry ice) if the process is not carefully controlled. Temperatures below -57 degrees Celsius introduce ductility concerns for the steel components and risked blocking the pressure communication connections within the BISEP that monitor seal annulus performance. There was no established method for managing this - STATS had to develop one.

BISEP - The Only Tool Capable of Proving the Isolation

Standard line-stop technology provides a mechanical barrier, but it cannot prove that barrier is leak-tight. For a supercritical CO2 system, that level of verification was non-negotiable. The BISEP isolation tool delivers double block and bleed isolation through a single hot tap penetration, with each of its dual elastomer seals independently pressure-tested before any breaking of containment. The annulus between the seals provides a monitored zero-energy zone for the duration of the isolation.

A 24-inch bypass line was installed around the isolated section to maintain continuous production throughout the workscope. Two 30-inch BISEPs provided mid-line isolation at each intervention location, with the bypass diverting product flow around the work site.

Hot Tapping a Supercritical System Under Full Operating Conditions

While the pipeline operated under normal conditions, the site contractor excavated the pipeline and welded split-tee fittings using qualified in-service welding procedures. Two 30-inch fittings at each location provided access for the BISEPs; two additional 24-inch fittings accommodated the bypass line. STATS installed their double block and bleed slab valves and used their SureTap hot tap drilling machine to break containment and recover the pipeline coupons under full operating pressure.

With the bypass line installed, purged, leak-tested and live, the BISEPs were deployed into the flowing pipeline and hydraulically set. During isolation barrier proving, each seal was tested independently at full pipeline pressure in the direction of the expected differential - confirming both seals of the double block isolation were leak-tight before any work on the isolated section began.

30” BISEPs isolating CO2 pipeline at 138 bar / 2000 psi with active bypass

Controlling CO2 Phase Change - the Critical Engineering Problem

The CO2 venting challenge was addressed through careful management of blowdown speed. By controlling the rate at which the isolated section was vented, the temperature of the CO2 could be kept above the design limits of the elastomer seals and the selected steel specification - preventing both seal degradation and the formation of dry ice within the tool.

Nitrogen was used to purge CO2 from the seal annulus, allowing pressure to be reduced in the annulus without bringing the temperature down to dangerous levels. The annulus could then be held at a pressure that was safe from a total contained energy perspective while remaining just high enough to prevent solid-phase CO2 formation. This managed approach to venting was a key development that made the entire operation possible.

The BISEP isolation capability has once again proven to offer compelling advantages over traditional line-stop technology for achieving provable, testable and monitorable double block and bleed pipeline isolation.

STATS Group logo
Project Manager
STATS Group
30in BISEP cw bypass site view from high up

Four Sites, 160-Plus Days of Isolation, Zero Leaks Past the Primary Barrier

STATS have completed isolations at four sites along the Cortez CO2 pipeline, all operating at around 138 bar (2,000 psi). Across those interventions, STATS have accumulated more than 160 days of individual BISEP isolation time. Throughout, there has been no degradation of the seals and no leaks past the primary barrier - allowing Kinder Morgan to carry out its launcher and receiver upgrades safely and without any uncontrolled release of pipeline product.

Careful selection of elastomer and steel materials for CO2 service, combined with pre-deployment testing and verification trials, were central to the consistency of performance across multiple sites. The managed approach to CO2 phase change during venting has since provided a repeatable methodology for future high-pressure CO2 interventions.

30in BISEP cw bypass site view showing diggers and pipeline

Tell us about your requirements